How many pavers, tonnes and bags do you need?

A typical Geraldton double driveway measures 5.6m by 8.0m, which is 45 square metres. That takes about 2,475 standard 200 by 100mm pavers laid herringbone, 8.5 tonnes of crushed limestone road base at 100mm compacted, 2.2 tonnes of bedding sand and 7 bags of stabilised jointing sand, and it digs out around 11 cubic metres of spoil. Size your own job below.

A Geraldton double driveway is usually 35 to 55 m². One car space is about 14 m². A 1.1m path is roughly 1.1 m² per metre of length.
Only the rounded pool edge or step nosings. Ordinary edge restraint is already included in the rate.
Extras on your site
What you need to order
Pavers, wastage included2,363
Crushed limestone road base8.6 t
Bedding sand at 30mm2.2 t
Stabilised jointing sand7 bags
Spoil to remove11 m³ (2 bins)
Pavers arriving on your verge5.0 t

Quantities are ordering guides. Buy the whole paver quantity in one delivery so it all comes from one batch, and keep about a square metre of spares.

Estimated range $3,400 - $5,000

Indicative Geraldton 2026 range, supplied and laid. A fixed price needs a site measure, and ours is free.

What the estimator assumes.

  • Rates include excavation, compacted crushed limestone base, screeded bedding sand, laying, cutting, edge restraint and stabilised jointing.
  • Road base is calculated at 0.19 tonnes per square metre per 100mm of compacted depth, which is the practical figure for Geraldton crushed limestone.
  • Bedding sand is 30mm compacted, so one tonne covers roughly 20 square metres.
  • Spoil assumes excavation to the base depth plus 30mm bedding plus the paver, bulked up 25 per cent once it is dug.
  • Paver weight assumes about 130 kilograms per square metre for a 60mm unit, which is what lands on your verge.
  • Excludes retaining walls, soakwells, drainage pits, crossover works and landscaping. Those are separate lines on a real quote.
Measuring

How to measure it properly with a tape and a phone.

Ten minutes with a tape beats any satellite tool, and it is the difference between a quote we can stand behind over the phone and a guess. Do it like this.

  1. Break the shape into rectangles. Almost every driveway, courtyard and alfresco is two or three rectangles with a bite out of one corner. Measure each rectangle in metres to one decimal place, multiply length by width, and add them together. Do not try to measure an L shape in one go.
  2. Measure at the widest point, not the average. Pavers are ordered for the widest part, and the offcuts from the narrow part are your wastage. Averaging is how people end up 40 units short on the last afternoon.
  3. Curves get the box treatment. Measure the smallest rectangle that fully contains the curve, then subtract roughly a third of each corner you are cutting off. It over-estimates slightly, which is exactly what you want when ordering.
  4. Measure the coping separately. Pool coping and step nosings are ordered by the lineal metre, not by area, and they cost $90 to $160 per lineal metre supplied and laid. Run the tape along the water line and write that number down on its own.
  5. Photograph the tape. At each measurement, take a photo with the tape in the shot. It takes two seconds and it settles every later argument about whether the driveway was 5.4 or 5.8 metres wide.
  6. Sketch it and send it. Draw the shape on paper, write the metres on each side, photograph the sketch and attach it to your quote request. A sketch with real numbers on it gets you an accurate figure the same day instead of a range.

Useful reference dimensions for Geraldton blocks: a single car width is 3.0 to 3.2 metres, a double driveway is 5.4 to 6.0 metres, a single parking bay is about 2.6 by 5.4 metres or 14 square metres, a comfortable path is 1.0 to 1.2 metres wide and 0.9 metres is the practical minimum, and a caravan or boat pad wants a full metre longer than the van plus room to swing the door. Note that the crossover, the bit between your boundary and the road, is not yours to size or specify: it is controlled by the City of Greater Geraldton and covered on our crossover paving page.

Send us the sketch and we will do the sums.

Photograph your measurements, attach them to a quote request, and we will come back with quantities and a fixed price after a free on-site measure.

Rules of thumb

The numbers a paver carries in his head.

  • Paver count per square metre. 200 by 100mm is 50, a 230 by 115mm brick paver is about 38, a 300 by 300mm slab is 11, a 400 by 400mm slab is 6.3, a 450 by 450mm slab is 5.
  • Wastage. 5 per cent straight bond, 10 per cent herringbone at 45 degrees, 12 per cent with curves, circles or a contrast border. Never zero.
  • Road base. 0.19 tonnes per square metre per 100mm compacted. A 45 square metre driveway is 8.5 tonnes at 100mm or 12.8 tonnes at 150mm.
  • Bedding sand. One tonne covers about 20 square metres at 30mm compacted.
  • Jointing sand. One 20 kilogram bag of stabilised sand covers roughly 5 to 10 square metres, depending on unit size and joint width. Small units mean more joint and more bags.
  • Edge haunch concrete. About one cubic metre per 60 to 70 lineal metres of edge, so most driveways need a quarter to half a cubic metre.
  • Spoil bulking. Ground swells about 25 per cent when you dig it. Eight and a half cubic metres in the ground is closer to 11 in the bin.
  • Paver weight. Around 90 kilograms per square metre at 40mm, 110 at 50mm and 130 at 60mm. A 45 square metre driveway in 60mm units is close to 6 tonnes sitting on your verge on 4 to 6 pallets.
  • Base overhang. The compacted base should extend past the paved edge by at least its own depth, so a 150mm base runs 150mm to 300mm wider than the pavers. Sizing the base to the paving exactly is a slow way to lose your edges.
The costly mistake

The sizing error that costs the most in Geraldton.

Under-ordering. Every time. Pavers are manufactured in batches, and colour drifts between production runs by an amount you would never notice on a pallet and cannot un-see across a driveway. If you order 2,250 units for a 45 square metre driveway with no wastage allowance, you will be 200 units short by mid-afternoon on laying day, and those 200 will come from whatever the yard has on the floor three weeks later. The fix is not a touch-up. The fix is lifting and relaying a whole section so the mismatch reads as a deliberate band. Ten per cent of extra units costs 10 per cent. Getting it wrong costs a section.

Second on the list, and specific to this town: sizing the driveway for the car and not the boat. A very large share of Geraldton houses keep a boat, a caravan or a camper trailer at home, and the hardstand that gets added two years later is where the paving mismatch problem shows up again. If a van is going to live beside the house, pave for it now, or at minimum lay the base and keep a pallet of the same batch under a tarp. A 6 metre van needs about 7 metres of hardstand plus room to swing the door and the tow vehicle in front of it.

Third, the base. People size the paved area carefully and then order base for exactly that area. The base has to run wider than the pavers so the edge restraint has something to sit on, and it has to be deep enough for the heaviest thing that will ever park on it, not the family car. If a concrete truck, a removal truck or a loaded boat trailer will ever be on it, that is a 150mm base conversation. Our specification page goes through the grades and depths, and how long paving lasts here shows what happens when the base was sized for the wrong vehicle.

Worked example

A four bedroom house in Wandina, added up.

Double driveway from the crossover to the garage, measured at 5.6 metres wide by 8.0 metres long, which is 44.8 square metres, call it 45. Plus a side path to the back gate, 1.1 metres by 9.0 metres, which is 9.9 square metres, call it 10. Total paved area 55 square metres. Driveway in 60mm concrete pavers laid herringbone at 45 degrees, path in 50mm units laid straight, 150mm base under the driveway because the family has a boat, 100mm under the path.

  • Pavers, driveway: 45 m² at 50 units per m² is 2,250, plus 10 per cent herringbone wastage equals 2,475 units.
  • Pavers, path: 10 m² at 50 units per m² is 500, plus 5 per cent equals 525 units. Total 3,000 units, roughly 6 pallets.
  • Road base: driveway 45 x 0.15 x 1.9 equals 12.8 tonnes, path 10 x 0.10 x 1.9 equals 1.9 tonnes. Order 15 tonnes.
  • Bedding sand: 55 m² at 0.048 tonnes per m² equals 2.6 tonnes. Order 3 tonnes.
  • Jointing sand: 55 divided by 7 equals 8 bags. Order 10 and keep the spares.
  • Edge haunch: 16 lineal metres down the two open driveway edges plus 9 along the open side of the path equals 25 lineal metres, or about 0.4 cubic metres of concrete.
  • Spoil: driveway 45 x 0.24 equals 10.8 cubic metres, path 10 x 0.19 equals 1.9, total 12.7 in the ground and about 16 cubic metres loose. Three bins of 6 cubic metres, roughly 20 tonnes to the Meru waste facility.
  • Paver weight on the verge: about 5.9 tonnes for the driveway and 1.1 for the path, so plan a firm drop zone that will take 7 tonnes on pallets.

The money on that job: 45 square metres of 60mm concrete driveway at $90 to $115 per square metre is $4,050 to $5,175, and 10 square metres of 50mm path at $80 to $105 is $800 to $1,050. Total $4,850 to $6,225 supplied and laid, before geotextile if the block is on soft sand and before removal if there is an old surface to take out. That sits right in the mid tier on our budget page, and the sequence it gets built in is on the day by day page.

One honest note to finish on. You do not need to work any of this out to get a price from us, and we would rather you did not order materials yourself. Supplying your own pavers loses you the trade price, leaves the shortfall and the breakage as your problem, and means nobody will warrant a unit they did not select. This page exists so you can sanity check a quote, plan a budget and understand what is turning up on your verge, not so you can do the ordering. If the numbers here do not match a quote you have been given by 20 per cent or more, that is a question worth asking before you sign, and our contractor guide and warranty page cover how to ask it.

Get a price

Send your measurements and get real quantities back

Attach or describe your measurements and we will book a free on-site measure, then email exact quantities and a fixed price, normally within one business day.

We reply within 1 business day. Free, no obligation.

Quantity questions we get asked.

How many pavers are in a square metre?
It depends entirely on the unit size. A standard 230 by 115mm clay brick paver is about 38 per square metre, a 200 by 100mm concrete paver is 50, a 300 by 300mm slab is 11, a 400 by 400mm slab is 6.3 and a 450 by 450mm slab is 5. Multiply by your measured area, then add the wastage allowance: 5 per cent for straight bond and 10 per cent for herringbone at 45 degrees.
How much road base do I need under paving?
About 0.19 tonnes of crushed limestone per square metre for every 100mm of compacted depth, so a 45 square metre driveway at 100mm needs roughly 8.5 tonnes, and the same driveway at 150mm needs about 12.8 tonnes. Order in whole tipper loads and allow a little extra, because you cannot compact what you do not have. Bedding sand is separate: one tonne covers about 20 square metres at 30mm.
How big is a typical double driveway in Geraldton?
Between 35 and 55 square metres. A double driveway is usually 5.4 to 6.0 metres wide, and the run from the crossover to the garage on most Geraldton blocks is 5 to 9 metres. Measure yours at the widest point rather than averaging, and remember the crossover itself is council controlled and priced separately.
How much wastage should I allow when ordering pavers?
Five per cent for straight stretcher bond, 10 per cent for herringbone at 45 degrees, and 12 per cent where there are curves, circles or a contrast border. Order the whole quantity in one delivery from one batch, because colour varies between production runs and a shortfall bought three weeks later will not match. Keep about a square metre of spares for future repairs.
How much spoil comes out of a driveway excavation?
Roughly 0.24 cubic metres per square metre for a 150mm base build, and the ground bulks up about 25 per cent once it is dug, so a 45 square metre driveway produces close to 13 cubic metres loose. That is two to three bins of 6 cubic metres, or somewhere around 15 to 20 tonnes. Tipping at the Meru waste facility is charged by the tonne, so spoil belongs on your quote as its own line.
What is the most expensive measuring mistake?
Under-ordering and then buying the shortfall from a different production batch, because the colour difference is permanent and the only real fix is relaying a whole section. The second most expensive is sizing the driveway for the car and not the caravan: adding 8 square metres two years later usually means the original paver has been discontinued. Measure the boat and trailer where you actually park them, then add a metre.

More reading: the Geraldton cost guide, driveway paving, pool surrounds, limestone versus brick and the suburbs we cover.